September 2022
Skeleton Constructions Completed
July 2022
Fifth Floor's Concrete Slab
June 2022
Second Floor's Concrete Slab
May 2022
Five months all constructions
April 2022
Proceeding The Ground Floor's Constructions
March 2022
The Ground Floor's Concrete Slab
January 2022
The Third Phase of The Concrete Slab
November 2021
The Typical Floor
October 2021
The First Concrete Slab of The Building