Construction Updates

September 2022

Skeleton Constructions Completed

July 2022

Fifth Floor's Concrete Slab

June 2022

Second Floor's Concrete Slab

May 2022

Five months all constructions

April 2022

Proceeding The Ground Floor's Constructions

March 2022

The Ground Floor's Concrete Slab

January 2022

The Third Phase of The Concrete Slab

November 2021

The Typical Floor

October 2021

The First Concrete Slab of The Building